Metro de Santiago power works reach 85%, but Línea 7 still needs an underground link

At Cerro Navia, high-voltage equipment is being integrated before crews connect the substation to the new railway tunnel.

Metro de Santiago power works reach 85%, but Línea 7 still needs an underground link

Why it matters: The Metro expansion depends on new transmission and transformation capacity at Cerro Navia, as well as the railway works themselves.

By the numbers:
  • 85% — reported progress on the electrical infrastructure for future Lines 7, 9 and A.

  • Two 220 kV bays — planned to connect the project to the high-voltage network.

  • Two 80 MVA transformers — equipment for receiving and transforming electricity.

  • 58 metres — length of the overhead interconnection line on monopole structures.

Metro de Santiago and Transelec said the electrical infrastructure for future Metro Lines 7, 9 and A is 85% complete, with work centred on the Cerro Navia substation in the Santiago Metropolitan Region. The project is now in systems integration and testing; a separate underground connection to Línea 7 remains ahead.

The companies presented the progress during a technical visit on 17 November. The reported percentage covers the electrical infrastructure, not construction of the three rail lines or their readiness to begin service. Once completed, the system is intended to supply Línea 7 first, with Lines 9 and A to follow as their development advances.

Cerro Navia works add high-voltage capacity

The project includes two new 220-kilovolt bays and two 80-megavoltampere power transformers, along with a 58-metre interconnection line carried on monopole structures. Safety systems and noise-mitigation measures are also part of the work.

Electricity from the transmission network will be transformed to medium voltage and distributed through Metro’s own installations. The process requires transformation, protection, measurement and switching equipment to operate together. Metro’s contractor, Alstom, has completed installation of equipment inside the medium-voltage compound, including circuit breakers, disconnectors and measurement systems. Transelec carried out the civil works and high-voltage installations.

The two companies are integrating the systems and checking their operation before energisation. The substation is designed to use Cerro Navia’s existing transmission infrastructure while accommodating the additional demand from the expanding rail network.

Underground connection is the next step for Línea 7

Metro’s next phase is to build an underground connection from the medium-voltage compound to the future Línea 7 tunnel. The company plans to use Tunnel Liner construction, assembling metal modules from inside the excavation. Metro’s project information said site preparations for this work were planned for November 2026; the work must be coordinated with railway construction and electrical testing.

The staged approach means the infrastructure will serve Línea 7 initially, then the planned Lines 9 and A. Metro board chairman Patricio Rey said Línea 7 will include three stations in Cerro Navia, a commune without direct Metro access. Transelec chief executive Arturo Le Blanc said the expansion of electric mobility requires transmission networks able to meet new transport demand.

The remaining work is to complete system checks, energise the medium-voltage compound and build the underground link. The 85% figure does not indicate that the three future lines are close to entering service.