Marimaca wins Chile early-works permit, but full mine build still needs approval
The authorization covers earthworks, not the full set of mine and processing facilities required for the 13-year operation.

Why it matters: The permit lets Marimaca begin physical work on a planned new copper mine, but it does not authorize the entire project or make its proposed financing available.
US$587 million — initial investment in the definitive feasibility study
50,000 tonnes a year — planned nameplate cathode copper capacity
179 million tonnes — proven and probable reserves at 0.42% total copper
Up to US$450 million — proposed Sprott financing package, still conditional
Marimaca Copper has secured Sernageomin’s Method of Mine Exploitation permit for its Marimaca Oxide Deposit project in Chile’s Antofagasta Region, allowing early works including site preparation and bulk earthmoving. The approval was granted to Compañía Minera Cielo Azul Limitada, a wholly owned subsidiary, and announced on November 26, 2026.
The permit is a step toward construction, not a final authorization to build and operate the mine. Marimaca still needs to complete other sectoral permitting and detail engineering, while the company’s board has yet to make a final investment decision (FID).
Permit covers early works, not the whole mine
Sernageomin’s approval complements the project’s favorable environmental approval, issued in November 2025. Marimaca submitted applications for key sectoral permits in April 2026 covering the open-pit mining method, mine closure plan, crushing facilities, leach pads, waste-rock and spent-ore deposits, and related processing infrastructure. The company said not all sectoral authorizations have been granted.
The distinction matters because environmental approval does not replace the technical permits required for individual mine and processing facilities. The new authorization enables initial ground works, while engineering, procurement and other permitting continue.
Feasibility study sets out a 13-year operation
Marimaca’s definitive feasibility study, released in August 2025, outlines an open-pit mine with heap leaching, solvent extraction and electrowinning to produce copper cathodes. It estimates average output of 48,000 tonnes annually during the first 10 years, against nameplate capacity of 50,000 tonnes a year, over a 13-year mine life.
The study reports 179 million tonnes of proven and probable reserves grading 0.42% total copper, containing 748,000 tonnes of copper. At an assumed copper price of US$4.30 per pound, it estimates an after-tax net present value of US$709 million and an internal rate of return of 31%. Estimated C1 operating costs are US$1.69 per pound, with all-in sustaining costs of US$2.09 per pound. Those are study estimates; actual performance will depend on construction costs, metallurgical results and market conditions.
Proposed funding still needs to close
Two days before the permit announcement, Marimaca said Sprott Resource Lending’s investment committee had approved a proposed financing package of up to US$450 million. It comprises a secured facility of up to US$425 million with a 7.5-year term and a potential equity investment of up to US$25 million. The total would equal about 77% of the study’s estimated initial capital.
Committee approval is not a disbursement. The financing remains subject to legal and financial due diligence, definitive agreements and other conditions. The proposal does not require copper-price hedging, according to the company.
The project is about 25 kilometres from Mejillones and less than 40 kilometres from Antofagasta. Marimaca said it obtained grid-connection authorization in October 2026 and agreed the main commercial terms for a renewable-energy supply. It also has an option for reused seawater from industrial facilities in Mejillones Bay. The next steps are to advance remaining permits and engineering, satisfy financing conditions and put the project before the board for an FID.
More in Resources
Aurora Williams named among 100 mining women as Chile faces a retention test
Hiring has lifted women’s share of Chilean large-scale mining, but staying and advancing remain separate tests.
Copper rebounds to US$5.58 as Codelco faces lower China premiums
Chinese purchases of Chilean cathodes have dropped, sharpening the stakes in Codelco’s annual supply talks.
Chile's copper export gains face a production squeeze as prices retreat from October highs
Higher export values are cushioning falling mine output, but that balance depends on prices holding above recent lows.



