Energy Fuels plans White Mesa uranium campaign as Pinyon Plain output faces decline
Pinyon Plain's expected decline puts four projects in focus, but each faces a different hurdle before it can contribute.

Why it matters: The planned campaign could bridge contracted uranium deliveries while Energy Fuels works to bring other sources into its production pipeline.
Nearly 1 million pounds — uranium concentrate planned for processing at White Mesa from December 2026 into the first quarter of 2027.
1.11 million pounds — U₃O₈ Energy Fuels projects selling under long-term contracts in 2027.
About 1.25 million pounds a year — potential combined production contribution from four projects, subject to development conditions.
400 wells — delineation wells drilled at Nichols Ranch's Jane Dough sector in 2026.
Energy Fuels plans to process nearly 1 million pounds of uranium concentrate at its White Mesa mill in Utah from December 2026 through the first quarter of 2027, using ore from Pinyon Plain in Arizona, the La Sal complex and other uranium-bearing materials. The campaign is intended to support deliveries under existing utility contracts as the company advances four projects it says could help offset an expected decline in Pinyon Plain production.
The material will be sent to a North American uranium conversion facility. Energy Fuels expects to apply the output to supply contracts running through 2028, with spot-market sales also possible depending on market conditions. After the uranium campaign, the company plans to return White Mesa to processing monazite for rare earth production, reserving mill time for that work through much of 2027 and into 2028.
Contracted sales depend on a shifting production base
Energy Fuels forecasts 2027 long-term contract sales of 1.11 million pounds of U₃O₈: 465,000 pounds in the first quarter, 270,000 in the second and 375,000 in the third, with no fourth-quarter deliveries scheduled. That is 35% above the 820,000 pounds it expects to sell under the agreements in 2026. Contractual flexibility allows volumes to range from 890,000 to 1.13 million pounds.
The company has six long-term contracts and says low-cost Pinyon Plain output supports its commitments. It reported average extraction, processing and transport costs of about US$23 per pound at the mine to date. For 2026, it forecasts production of 1.6 million to 2 million pounds of mined and produced uranium. Energy Fuels said in December 2025 that it had exceeded its annual projections after extracting more than 1.6 million pounds.
Four projects are at different stages
At Whirlwind, on the Colorado-Utah border, the company has dewatered and rehabilitated the underground access and begun mine development. First production is scheduled for 2028, subject to permits and market conditions. Its resource figures come from a 2011 technical report and are historical, not current estimates; further drilling may not confirm them.
At Utah's Energy Queen, work is under way to rehabilitate the hoist system and upgrade electrical facilities. A 2022 technical report estimates an Inferred Resource of 750,000 pounds of U₃O₈ at an average grade of 0.25%. The mine produced 12,800 tonnes of ore at 0.164% from 1981 to 1982, equivalent to 41,922 pounds of uranium.
Bullfrog is carrying out a four-well groundwater monitoring programme to establish baseline conditions for permitting. One well was complete, and the company expected the other three to be finished by the end of 2026. A May 2025 initial assessment estimated Indicated Resources of 10.51 million pounds and Inferred Resources of 3.42 million pounds, at average grades of 0.303% and 0.279%, respectively.
At Wyoming's Nichols Ranch, an existing in-situ recovery operation in reduced-operation status, Energy Fuels drilled 400 delineation wells in the Jane Dough sector in 2026. Of these, 38 recorded a grade-thickness interval above 1.1, while 102 fell between 0.25 and 1.1 and 145 between 0.01 and 0.25; the remaining 115 showed trace or no measurable mineralisation. The work is intended to refine resource locations and wellfield design ahead of a potential restart. The four projects could add about 1.25 million pounds of annual production, according to the company, subject to project progress, permitting where required and investment decisions.
More in Resources
Bank of America sees Chilean peso recovery in 2027, but sets no target
The dollar recently traded near $1,020 in Chile, while the bank’s thesis depends on a reversal in copper and oil conditions.
GreenLight’s Bend drilling plan advances in Wisconsin, but tribal concerns persist
The federal proposal covers less than eight acres, but representatives say its safeguards do not fully address wetlands and cultural sites.
Ivory Coast registers citizens after Guinea gold closures, but returns are not automatic
The consular search reaches six Forest Guinea prefectures and includes people whose livelihoods depended on the closed sites.