Chile’s O’Higgins 220 kV line faces a connection deadlock after workaround rejected
The line is built, but its planned tie-ins depend on substation works delayed by failed tenders.

Why it matters: The decision leaves a planned transmission upgrade unavailable until linked substation and connection works are completed to the required technical standards.
About 25 km — planned length of the Candelaria–Nueva Tuniche line
220 kV — design voltage, with two circuits
400 MVA per circuit — planned transmission capacity
48 months — original construction period under the 2020 award
Chile’s Ministry of Energy rejected Transelec’s request to modify the technical characteristics of its Candelaria–Nueva Tuniche 2x220 kV line and Nueva Tuniche substation project in the O’Higgins Region. The decision, reported on November 19, 2026, blocks the company’s proposed temporary connection to an existing 154 kV circuit while complementary works remain delayed.
The rejection was set out in Ministerial Exempt Resolution No. 79, following adverse assessments from the National Energy Commission (CNE) and the National Electric Coordinator. The project itself remains in place, but the ministry did not authorize the alternative that Transelec said could bring its constructed infrastructure into service before all planned connections were ready.
Delays in linked expansion works
Transelec applied on January 15, 2026, saying it had completed the first three relevant construction milestones but could not complete the fourth and fifth because of delays to complementary works. The company said the delays were preventing it from operating infrastructure already built and receiving the associated operating revenue.
The required works include an expansion of Candelaria substation, new connection bays on the Punta de Cortés–Tuniche line and an additional transformer at Punta de Cortés substation. These installations must be available to connect the new line to the system as originally planned.
Some of the related projects encountered difficulties in procurement. The Candelaria substation expansion went through a new tender that ended without an award. Other expansions associated with Punta de Cortés also had to be retendered. In its January 2026 expansion report, the Coordinator identified the Candelaria work as an unsuccessful tender and said Celeo planned to tender it again.
Why the 154 kV alternative failed
Transelec proposed a tap-off connection to the existing 154 kV Tap Tuniche–Rancagua circuit, along with changes to the timing and conditions of outstanding construction milestones. The company’s proposal was intended as an interim route around the delayed works, rather than a replacement for the project’s planned configuration.
The CNE found that the alternative would not preserve the technical conditions or system benefits envisaged in the original plan. It questioned whether a single-circuit connection at a lower voltage could functionally substitute for a two-circuit 220 kV line and raised concerns about compliance with the Technical Standard for Security and Quality of Service.
The Coordinator also withheld technical approval. Its concerns included protection arrangements, fault selectivity and service continuity—the safeguards intended to prevent a fault at one point from triggering unnecessary disconnections or affecting other facilities.
No new commissioning date
Article 151 of Chile’s Transmission Systems Regulation allows technical changes to expansion works under specified conditions and with unanimous agreement among the required parties. The CNE’s and Coordinator’s adverse assessments meant that agreement was not achieved, and the ministry rejected the requested modification.
The ruling does not cancel the awarded project or set a new date for commissioning. Service remains contingent on resolving the delays and making the required connections available under current technical rules. The Coordinator has also warned that the missing Candelaria expansion poses risks to the 154 kV system between Alto Jahuel and Tinguiririca, recommending operational measures to address potential failures while the necessary investments proceed.
More in Resources
Copper drops to US$5.54/lb as London inventories rise and losses extend
The nine-session slide has pushed Chile’s benchmark export below its 2026 average as traders reassess industrial-demand signals.
Moody’s sees Chilean companies under 2027 cash-flow pressure as copper capex rises
Falling ore grades, longer haul distances and water infrastructure are adding to the spending burden across Chile’s copper mines.
Sernageomin reviews safety systems at Pucobre and Candelaria in Atacama
One operation was underground and the other an open pit, putting emergency readiness and operational controls under different tests.