A scheduled plant shutdown explains the October dip, but the operating comparison now hinges on an underground zone that was still ramping up.

Why it matters: The gap between October’s lower mill output and faster underground extraction will test how quickly Sleeping Giant can restore throughput after scheduled maintenance.
5,581 tonnes — ore processed at Sleeping Giant in October, down from 6,739 tonnes in September.
336 ounces — gold produced in October, compared with 740 ounces in September.
4,070 tonnes — Zone 20 ore mined by November 19, exceeding the mine’s total October underground extraction.
91.4% — October gold recovery, against 94.1% in September.
Abcourt Mines processed 5,581 tonnes of ore at its Sleeping Giant gold mine in Quebec in October, as a scheduled maintenance shutdown near month-end reduced activity. The company reported production of 336 ounces of gold, down from 740 ounces in September. Underground mining at Zone 20 had picked up by November 19, when extraction there reached 4,070 tonnes—more than the 3,080 tonnes mined underground across the operation during all of October.
Planned maintenance cut October throughput and production
October mill feed averaged 2.05 grams of gold per tonne, with recovery of 91.4%. The plant poured 246 ounces into doré bars. A further 832 ounces remained in the plant circuit at month-end; that figure represents gold in process, not metal already poured.
In September, Sleeping Giant processed 6,739 tonnes at an average grade of 3.42 g/t and achieved 94.1% recovery. Doré pours fell from 545 ounces to 246 ounces in October. Abcourt attributed the lower activity to planned maintenance intended to support the reliability of the facilities.
Underground extraction totalled 3,080 tonnes at an average grade of 1.99 g/t. Development headings supplied 1,812 tonnes and long-hole stopes contributed 1,268 tonnes. The mine completed 111 metres of development, raising 3,334 tonnes of ore and 2,471 tonnes of waste.
Definition diamond drilling reached 4,108 metres, which the company said exceeded its monthly target. Long-hole drilling and blasting included 1,039 metres drilled and 812 tonnes blasted, at a reported average grade of 5.00 g/t gold.
Zone 20 extraction outpaced October’s mine total
Zone 20 had been in production since September 2026, with mining planned to continue through January 2027, Abcourt said. Its 4,070 tonnes mined by November 19 exceeded the 3,080 tonnes extracted underground during October. The comparison covers different periods: the Zone 20 figure is a November-to-date total, while the October figure is the whole mine’s monthly extraction.
A 2023 preliminary economic assessment estimated 9,487 tonnes at 5.66 g/t for the remaining Zone 20 stope. That is a study estimate, not material already mined.
At Zone 785N on level 915, the company reported 7,454.3 metres of drilling and estimated that 105 to 120 metres of development remain before reaching the zone. Abcourt said the area could contain two economic veins. Its 2023 preliminary assessment estimated potential of 20,203 tonnes at 8.46 g/t and an access period of four to five months with the current workforce. These are company estimates; the update did not report that the material had been accessed or extracted.
Three-year labour agreement ratified by workers
Abcourt signed a new collective agreement for Sleeping Giant on November 16 after six days of negotiations. All workers ratified the agreement, which runs for three years. The company did not disclose wage terms or other agreement provisions.
The company also said six of 10 students in a mineral-extraction programme at the Centre de formation professionnelle de la Baie-James will be hired as apprentice miners after completing their training on November 24. A new group of 12 students is scheduled to begin training on November 25, with the programme running through March 2027. The technical information in the update was reviewed and approved by Abcourt chief executive Pascal Hamelin, whom the company identifies as a qualified person under NI 43-101.
More in Resources
Bank of America sees Chilean peso recovery in 2027, but sets no target
The dollar recently traded near $1,020 in Chile, while the bank’s thesis depends on a reversal in copper and oil conditions.
GreenLight’s Bend drilling plan advances in Wisconsin, but tribal concerns persist
The federal proposal covers less than eight acres, but representatives say its safeguards do not fully address wetlands and cultural sites.
Energy Fuels plans White Mesa uranium campaign as Pinyon Plain output faces decline
Pinyon Plain's expected decline puts four projects in focus, but each faces a different hurdle before it can contribute.