BLM advances Century Lithium’s Angel Island review, but mine approval remains ahead

Nevada’s proposed open pit, processing plant and water infrastructure are all within the scope of the federal environmental review.

BLM advances Century Lithium’s Angel Island review, but mine approval remains ahead

Why it matters: Angel Island’s path to development depends on a federal environmental review that is still underway, not on the BLM’s acceptance of baseline studies.

By the numbers:
  • 5.5 million tonnes a year — proposed ore processing rate

  • 27,400 tonnes a year — estimated average lithium carbonate output

  • US$1 billion — approximate initial capital investment

  • 4 February 2028 — FAST-41 target date for a federal decision

The US Bureau of Land Management (BLM) has completed its review of baseline environmental information for Century Lithium’s Angel Island project in Nevada and determined that the proposed mine must undergo an Environmental Impact Statement (EIS). The decision moves the project into federal environmental review but does not authorize construction or operation.

The determination was set out in a 13 November 2026 letter to Cypress Holdings (Nevada), a wholly owned Century Lithium subsidiary. The BLM said the baseline information addressed the resources identified by its interdisciplinary team, including additional studies of the water pipeline route and well field.

EIS review still stands between Angel Island and a decision

The BLM’s Tonopah office, within the Battle Mountain District, will lead the EIS under the US National Environmental Policy Act and Department of the Interior procedures. The Environmental Protection Agency, Nevada Department of Wildlife and Esmeralda and Nye counties will participate as cooperating agencies; that role does not signify approval of the project.

The baseline review follows a separate BLM determination on 9 November that Century Lithium’s mine operations plan and Nevada reclamation permit application were complete under applicable federal regulations. A third-party contractor will continue preparing a supplemental information report to support supplemental environmental reports and the EIS.

The operations plan may be adjusted after public participation, including the scoping process, and environmental analyses are completed. The BLM could issue a formal Record of Decision (ROD) only after those stages. The agency’s finding on baseline information therefore does not determine the outcome of the review.

Proposed mine would process 5.5 million tonnes of ore annually

The proposed development in Esmeralda County includes an open-pit mine, two waste-rock stockpiles, two low-grade ore stockpiles and a dry-stack tailings facility. The plan also includes roads, support buildings and a processing and leaching plant. Century Lithium owns the project outright.

The design calls for processing 5.5 million tonnes of ore annually, equivalent to a nominal rate of 15,000 tonnes per day, and average output of 27,400 tonnes of lithium carbonate per year. These are design estimates, not current production. The company said the figures are based on an updated feasibility technical report for Clayton Valley, the project’s former name, with an effective date of 3 January 2026. The company has estimated initial capital at about US$1 billion.

Century Lithium describes the proposed operation as an integrated lithium carbonate development using hydrochloric acid leaching and direct lithium extraction. The company’s technical disclosure notes that mineral resources not classified as reserves do not have demonstrated economic viability. Daniel W. Kalmbach, the company’s vice-president of exploration and resource development, reviewed and approved the technical information as a non-independent Qualified Person under NI 43-101.

FAST-41 target date is not a permit or construction date

Angel Island is listed as a transparency project under the federal FAST-41 programme. Its federal permitting dashboard gives 4 February 2028 as the target date for issuing the ROD. The schedule may change as the review proceeds and is not a guaranteed approval date or a forecast for construction.

The next stages include continued preparation of supplemental information, public participation and environmental analysis. The BLM’s formal decision will follow those steps, while Century Lithium continues the federal and state permitting process.