Eldorado starts four Skouries filters, but design throughput needs five
The Greek project is nearing a commercial-production milestone, while its tailings circuit remains short of the configuration required for full throughput.
The Greek project is nearing a commercial-production milestone, while its tailings circuit remains short of the configuration required for full throughput.
The northern Greece mine has started commissioning its tailings system, but commercial readiness and nameplate processing hinge on different operating thresholds.
Skouries has already produced its first copper-gold concentrate, but commercial output still depends on the circuit’s commissioning.