MONDAY, NOVEMBER 23, 2026 · GLOBAL EDITION (EN) · EDICIÓN LATAM (ES)

Eldorado starts four Skouries tailings presses, but full throughput needs five

Skouries has already produced its first copper-gold concentrate, but commercial output still depends on the circuit’s commissioning.

Eldorado starts four Skouries tailings presses, but full throughput needs five

Why it matters: Skouries’ move from commissioning to commercial production depends on getting its tailings filtration circuit operating reliably as processing ramps up.

By the numbers:
  • 4 of 6 presses — operating; Eldorado says this configuration can support commercial production of sulphide ore.

  • 5 presses — required for the mine to reach nominal throughput.

  • Early December 2026 — the company’s target for the two remaining units to enter service.

  • Late Q4 2026 — Eldorado’s target for commercial production, subject to commissioning and ramp-up.

Eldorado Gold has put four tailings filter presses into operation at its Skouries gold-copper mine in northern Greece, meeting the equipment threshold the company says is needed to support commercial production of sulphide ore. Reaching nominal throughput will require a fifth press to be operating. Eldorado expects the two remaining presses to be in service by early December and continues to target commercial production toward the end of the fourth quarter of 2026.

The schedule remains dependent on commissioning and ramp-up. Skouries produced its first copper-gold concentrate on September 8, during plant commissioning. The start of commercial production has not yet been achieved.

Filtration capacity is not the same as nominal throughput

The installation includes six Metso presses: five intended to operate and one installed as a spare. Eldorado says four operating presses meet the requirement to support commercial production of sulphide ore, while a fifth is needed for nominal operating throughput. The spare is intended to provide operational flexibility and allow maintenance without losing processing capacity.

The company has not disclosed the treatment capacity of each press or the processing rate achieved to date. The number of units in service therefore does not establish Skouries’ current throughput or show how quickly the plant can reach its nominal rate.

Chief executive Christian Milau said the added filtration capacity would support progress in throughput and commissioning. Actual performance will depend on the presses and associated infrastructure operating as required, alongside a gradual increase and stabilisation of processing. Eldorado’s update follows the start-up of the first two presses, which the company reported on October 26.

Commercial production remains a year-end target

Eldorado’s target of commercial production by late in the fourth quarter depends on commissioning and ramp-up being completed on schedule. The company identifies press performance and availability, the commissioning of related infrastructure and the plant’s ability to achieve stable throughput as factors in reaching that point.

Eldorado shares traded at US$24.75 on the New York Stock Exchange on November 20, down 31.1% year to date. The company did not provide new production, capital or operating-cost estimates for Skouries in this update.

Technical report update planned for 2027

Eldorado expects to publish an updated Skouries technical report in the first quarter of 2027. The update is expected to include a revised resource model, new metal-price assumptions and updated production, operating-cost and capital estimates reflecting the project’s transition from development to operations.

That timing is also a company projection and depends on completing the resource model and revised estimates as planned. In the near term, the operational milestones are the expected start-up of the remaining presses and progress toward stable plant throughput.