Eldorado brings four Skouries filters online, but full throughput needs another

The northern Greece mine has started commissioning its tailings system, but commercial readiness and nameplate processing hinge on different operating thresholds.

Eldorado brings four Skouries filters online, but full throughput needs another

Why it matters: Skouries’ ramp-up depends on tailings filtration, while the gap between commercial production and nominal throughput leaves a key operating benchmark ahead.

By the numbers:
  • 4 presses — the number Eldorado says can support commercial production with sulphide ore.

  • 5 presses — required to reach the plant’s nominal processing capacity.

  • 6 presses — installed at the filtration facility, including one reserve unit.

Eldorado Gold has brought four tailings filter presses into operation at Skouries, its gold-copper mine in northern Greece. The company said that level can support commercial production with sulphide ore, but five presses must be operating for the plant to reach nominal processing capacity. Eldorado expects commercial production around the end of the fourth quarter of 2026.

The distinction means the current operating status does not demonstrate that Skouries has reached full throughput. The company did not report processed tonnage or filter performance metrics in its update.

Five presses are needed for nominal capacity

The filtration facility has six Metso presses: five intended for operation and one installed as a reserve. The first two began operating on October 26, 2026. Eldorado expects the two remaining units to enter service in early December; one of those is the reserve press.

The company said the four presses now running provide the capacity needed to support sulphide-ore commercial production. A fifth operating press is required for nominal plant processing. The additional reserve is intended to give the mine more flexibility during maintenance, allowing work to proceed without a loss of processing capacity. That benefit will depend on equipment availability and performance as the system moves through commissioning.

Chief executive Christian Milau said the available filtration capacity would allow processing to advance and operations to stabilise. Eldorado did not provide a date for reaching nominal capacity, nor did it disclose throughput figures. As a result, the number of presses in operation is a commissioning milestone, not a measure of achieved plant output.

Updated technical report expected in 2027

Eldorado plans to publish an updated technical report for Skouries in the first quarter of 2027. It expects the report to include a revised resource model, updated metal-price assumptions and new production, operating-cost and capital estimates as the project transitions from development to operations. The company has not yet provided those revised estimates or said how they will compare with previous technical figures.

The commercial-production and reporting timelines remain company projections. Eldorado has identified timely start-up of the remaining presses, progressive processing and stable plant performance among the assumptions behind its ramp-up plan; construction, operating, permitting and input-availability factors could affect timing. Its next stated operating milestone is bringing the two pending presses into service in early December.