Vizsla Silver moves Pánuco to 2028, with a safe site return still unresolved

Engineering is advancing away from site, but Pánuco’s construction phase still lacks its main mining contractor.

Vizsla Silver moves Pánuco to 2028, with a safe site return still unresolved

Why it matters: Pánuco’s revised schedule shows that engineering and early procurement cannot secure a mine timeline while a safe return to site remains uncertain.

By the numbers:
  • US$238.7 million — initial capital in the November 2025 feasibility study

  • 50% — engineering completed; about 85% of processing equipment has been ordered

  • 17.4 million ounces — projected average annual silver-equivalent production

  • 9.4 years — initial projected mine life

Vizsla Silver has moved the planned start of production at its Pánuco silver-gold project in Sinaloa, Mexico, to the second half of 2028 from the second half of 2027. The company cited security conditions, preparations for a return to site, and permitting and construction timelines. Its initial capital estimate remains US$238.7 million, but Vizsla has not updated the project economics to account for the revised schedule.

The update, presented on November 19, 2026, follows the kidnapping and murder of 10 workers linked to the project in January. In-person activities were suspended as the company reviewed conditions for resuming work. Vizsla is coordinating with Mexican federal authorities and security advisers, and says any return will be gradual and depend on its assessment of conditions. It has not set a date for a full resumption of site operations.

Engineering advances while site work remains constrained

M3 Engineering & Technology has completed about 50% of the project’s engineering, and Vizsla has ordered approximately 85% of the processing equipment. Those activities allow technical work and procurement to progress away from the site, but orders do not mean equipment has been delivered or installed.

The company has awarded three principal contracts covering engineering, procurement and construction management, mine design, and equipment supply. The main mining contract has yet to be awarded. Pánuco remains in preparation, rather than full-scale construction, and Vizsla has not made a definitive production decision.

The company is also developing a foundation for social programmes in Sinaloa, with an initial US$5 million commitment. Planned areas include education, health and local economic development, alongside support for families affected by the January events. The foundation’s structure and programmes are still being developed with nearby communities.

Feasibility economics have not been recalculated

The November 2025 feasibility study envisages initial processing capacity of 3,300 tonnes per day, rising to 4,000 tonnes per day from the fourth year. It projects average annual production of 17.4 million ounces of silver equivalent, increasing to 20.1 million ounces a year during the first five years. Over the initial mine life, payable production is projected at 94.7 million ounces of silver and 776,000 ounces of gold. Silver-equivalent production converts the value of gold using price assumptions; it is not a measure of physical silver output alone.

The study estimated all-in sustaining costs of US$10.61 per ounce of silver equivalent and sustaining capital of US$287.3 million. Its after-tax net present value was US$1.8 billion at a 5% discount rate, based on assumed prices of US$35.50 per ounce of silver and US$3,100 per ounce of gold. The model also estimated a 111% after-tax internal rate of return and a seven-month payback period.

Those figures belong to the original feasibility case. Vizsla has not recalculated them for the delay, possible cost changes or revised financing conditions. A later production start can shift the timing of cash flows, while additional costs could arise from security, staffing, equipment and site maintenance. The company has not published a revised estimate quantifying those effects.

Permits and contractor award remain on the path to production

Vizsla’s plan calls for detailed engineering, contracting, site preparation and permitting before production. The second half of 2028 is a target, not a guaranteed start date; the company says a production decision depends on completing and reviewing detailed engineering, financing arrangements and required authorisations.

The next steps also depend on awarding the main mining contract and establishing conditions for workers and contractors to return safely. Engineering and procurement are progressing, but the schedule remains contingent on those outstanding requirements and the company’s security assessment.