Spartan Metals’ Victorio PEA sets US$683m initial cost, but estimates remain preliminary

A block-caving design underpins the New Mexico plan, while resource classification and metallurgy still need further testing.

Spartan Metals’ Victorio PEA sets US$683m initial cost, but estimates remain preliminary

Why it matters: Victorio could add a US tungsten source to a supply chain concentrated in China, but its preliminary economics include inferred resources.

By the numbers:
  • US$683 million — estimated initial capital

  • 30.9% — after-tax internal rate of return in the base case

  • 24 years — planned operating life

  • ±50% — estimated accuracy range for capital and operating costs

Spartan Metals’ preliminary economic assessment (PEA) for the Victorio project in Luna County, New Mexico, outlines a 24-year underground tungsten and molybdenum mine with an initial capital cost of US$683 million and an after-tax net present value (NPV) of US$2.143 billion at an 8% discount rate. The base case estimates an after-tax internal rate of return (IRR) of 30.9%.

The project, about 45 kilometres west of Deming, is designed to process 25,000 short tons of ore per day, equivalent to approximately 22,680 metric tonnes. SRK Consulting led the technical work. The PEA estimates three years for construction and a payback period of about 3.2 years from the start of operations.

Block caving would feed separate tungsten and molybdenum circuits

The conceptual mine plan uses block caving, an underground method intended to extract large volumes of ore through gravity-driven rock fragmentation. Victorio’s proposed processing route includes a flotation circuit to recover molybdenum and a separate plant to produce ammonium paratungstate (APT), an intermediate tungsten product.

Over the mine life, the study forecasts processing about 199.5 million short tons of mineralized material. It estimates cumulative recovered production of 217.8 million pounds of tungsten trioxide (WO₃) contained in APT and 207.6 million pounds of molybdenum in concentrate. Average annual output is projected at 9.07 million pounds of WO₃ and 8.65 million pounds of molybdenum. These are PEA projections, not assured production; the tungsten figure refers to WO₃ content, not the weight of finished APT.

The model uses long-term prices of US$1,350 per metric tonne unit (mtu) of WO₃ and US$20 per pound of molybdenum. On those assumptions, estimated life-of-mine revenue is US$16.620 billion, operating costs are US$4.355 billion and cumulative after-tax free cash flow, undiscounted and before financing costs, is about US$6.903 billion.

Price sensitivity and capital requirements shape the economics

The PEA’s higher-price case uses US$2,000 per mtu of WO₃ and US$25 per pound of molybdenum, producing an estimated after-tax NPV of US$4.018 billion and IRR of 43.3%. At US$750 per mtu of WO₃ and US$15 per pound of molybdenum, the study estimates an NPV of US$392 million and IRR of 14.0%. Market reference prices cited for November 13, 2026, were about US$2,650 per mtu for APT and US$34.23 per pound for molybdenum; the study cautions that reference prices may not match the prices Victorio could realize under future contracts.

The US$683 million initial estimate comprises US$224.7 million for mine development, US$296.2 million for processing facilities and US$162 million for infrastructure. The PEA also estimates US$2.031 billion in sustaining capital over the operating life, bringing initial and sustaining capital to about US$2.714 billion. Cost estimates carry an accuracy range of approximately plus or minus 50%, consistent with the study’s preliminary level.

Further drilling and studies precede a development decision

Spartan Metals has identified about US$13.2 million of work to advance Victorio toward a prefeasibility study. The proposed programme includes drilling, geotechnical and hydrogeological work, environmental studies and further design of the tailings storage facilities. It is also intended to improve the classification of inferred resources and investigate near-surface tungsten mineralization.

The October 2026 resource estimate contains 84.54 million short tons of Measured and Indicated resources and 101.84 million short tons of Inferred resources. The PEA includes some Inferred material, which is too geologically speculative to be treated as mineral reserves and adds uncertainty to the economic case. The study assumes recoveries of 85% for molybdenum and 72.75% for WO₃ across recovery and APT processing; further representative test work is needed to verify those assumptions.

Spartan holds an option to acquire 100% of Victorio, subject to contractual conditions. Before a construction decision, the project would need more detailed engineering, permitting, financing and further work on water supply, geotechnical conditions and operating costs. The company’s proposed next step is the prefeasibility-stage work programme.