Agnico Eagle targets 1 million ounces at Canadian Malartic; second shaft still under study

Odyssey’s first shaft is 73% complete, while the deeper expansion still needs a separate technical and permitting path.

Agnico Eagle targets 1 million ounces at Canadian Malartic; second shaft still under study

Why it matters: The plan would shift Canadian Malartic further underground and rely on existing processing capacity to handle ore from deeper workings and satellite deposits.

By the numbers:
  • 950,000–1.05 million ounces a year — projected combined output at Canadian Malartic by 2033

  • 1,586 metres — planned depth of Odyssey’s first production shaft

  • 1.6 million ounces — probable gold reserves at Marban

  • 2030 and 2032 — projected production starts for Upper Beaver and Hammond Reef, respectively

Agnico Eagle Mines is targeting annual gold production of about one million ounces at its Canadian Malartic complex in Quebec by 2033, combining the Odyssey underground mine with the Marban and Wasamac deposits. The company’s plan implies a range of 950,000 to 1.05 million ounces a year, but depends in part on a second Odyssey shaft that remains at the study stage.

The update, dated November 18, also outlines separate growth projects at Upper Beaver and Hammond Reef in Ontario. Their projected schedules and production rates remain subject to technical work, permits and investment decisions.

Odyssey’s second shaft is a key part of the expansion

The first Odyssey shaft is 73% complete and is designed to reach 1,586 metres. Initial production through the shaft is planned for June 2027, with a first loading station expected in the second half of that year and a second station planned for 2029. Odyssey is already mining by ramp access, and extraction from the East Gouldie deposit began in 2026. The Barnat open pit and stockpile processing are expected to continue until 2029.

Agnico is studying a second shaft, with a conceptual design reaching 1,740 metres and measuring 6.7 metres in diameter. The company estimates it could move 8,000 to 10,000 tonnes of ore daily and add 200,000 to 250,000 ounces of annual gold production. Technical studies are expected to finish in the second half of 2027, followed by planned permit amendments in 2028. Production associated with the shaft is projected to begin in 2033.

The expansion also relies on deposits beyond Odyssey. Marban, about 12 kilometres from the processing plant, is planned as an open-pit mine producing an estimated 120,000 to 150,000 ounces a year. Its probable reserves are 1.6 million ounces, contained in 51.6 million tonnes grading 0.95 grams of gold per tonne. Ore would be trucked to Canadian Malartic, requiring new transport infrastructure across a road and railway. Technical studies are due in the second half of 2027, with federal and provincial authorizations planned for 2031.

Wasamac is a proposed underground satellite that could contribute 80,000 to 100,000 ounces annually from 2033. Canadian Malartic’s existing plant has capacity of about 60,000 tonnes a day, giving the company a route to process ore from satellite deposits without building a separate plant for each one.

Ontario projects add gold and copper to the pipeline

At Upper Beaver, in the Kirkland Lake district, Agnico projects about 210,000 ounces of gold and 3,600 tonnes of copper annually. The proposed underground operation would initially process 5,000 tonnes a day, with potential to expand to 8,000. A planned exploration shaft would first reach 760 metres, with a possible extension to 1,220 metres. Access to the 160-metre level is expected in the first half of 2027 to collect a representative mineral sample. Updated technical studies are scheduled for the second quarter of 2027, and production is projected to ramp up from the first half of 2030, subject to permits.

Hammond Reef, near Atikokan, is a proposed open-pit operation with two pits, a projected mine life of 13 years and annual gold production of 250,000 to 300,000 ounces. Its probable reserves total 3.3 million ounces in 123.5 million tonnes grading 0.84 grams per tonne. The preliminary design includes a 33,500-tonne-a-day processing plant, a 19-kilometre, 230-kilovolt power line and upgrades to 38 kilometres of access roads. Updated technical work is planned for the second quarter of 2027, with a potential development decision in 2029 and production targeted for 2032.

OR Royalties, which holds royalties on parts of the complex and on Upper Beaver and Hammond Reef, said its current portfolio could support nearly 50% growth in attributable gold-equivalent production by 2030. Agnico’s project schedules remain dependent on completing studies and securing the required authorizations; several of the expansion components are not yet in production or fully permitted.