Newcore Gold seeks Enchi mining lease, but Ghana's environmental review remains ahead
The proposed open-pit mine has a prefeasibility case, but the mining lease would clear only the first regulatory gate.

Why it matters: Enchi's proposed US$351 million development now faces a permit sequence that leaves environmental approval and financing unresolved.
53.37 km² — area covered by the mining lease application within the 248 km² Enchi property
US$351 million — estimated initial capital in the June 2026 prefeasibility study
104,000 ounces — projected average annual gold production
9.3 years — estimated initial mine life
Newcore Gold has applied for a mining lease covering 53.37 km² of its Enchi gold project in southwestern Ghana, beginning a formal step toward developing a proposed open-pit mine. The company expects the application review to conclude in the first half of 2027. If the lease is granted, it must then seek environmental approval before construction or commercial production can proceed.
The Canadian company’s application follows a prefeasibility study completed in June 2026. That study outlines initial capital of US$351 million and average annual production of approximately 104,000 ounces of gold. The application is not an authorization to build or operate the mine, and a final investment decision would also depend on permitting, technical work and financing.
Prefeasibility plan projects 953,350 payable ounces
Enchi’s proposed mine would use conventional open-pit mining by contractors and a processing plant combining milling with carbon-in-leach (CIL) technology. The design calls for processing capacity of 5.5 million tonnes of ore a year, with average recovery estimated at 90.5% and an average mined grade of 0.64 g/t gold.
The study projects 953,350 payable ounces over the initial 9.3-year mine life. Production is forecast to average 130,000 ounces annually during the first three years, when the mine plan is expected to access higher-grade areas, before averaging approximately 104,000 ounces a year across the full schedule.
The economic case is sensitive to gold-price assumptions. At US$3,800 per ounce, the study estimates an after-tax net present value of US$496 million at a 5% discount rate, an after-tax internal rate of return of 37% and a 1.6-year payback period. At US$4,200 per ounce, it estimates an after-tax net present value of US$647 million and a 45% internal rate of return. The projected life-of-mine all-in sustaining cost is approximately US$2,290 per ounce. These are study scenarios, not guaranteed returns.
Mining lease review precedes environmental application
Ghana’s Ministry of Lands and Natural Resources and the Minerals Commission are involved in the lease review. The company is targeting a decision in the first half of 2027, although the timing remains subject to the review process. A mining lease would allow Newcore to proceed with a formal environmental authorization application to Ghana’s Environmental Protection Authority; it would not replace that assessment.
Newcore says it has collected environmental and social baseline data at Enchi since 2015, with studies also conducted in 2023, 2024, 2025 and 2026. Work has covered water and soil quality, noise and air quality. Baseline studies inform an assessment but do not constitute environmental approval, which must consider the proposed mine, processing facilities, tailings management and related infrastructure.
Drilling continues beyond the proposed mine area
The lease application covers part of the 248 km² property, which extends across about 40 kilometres of the Bibiani Shear Zone. Newcore is also conducting an 80,000-metre drilling programme to test extensions and deeper, higher-grade mineralization. The resource estimate used in the prefeasibility study included geological information through October 2025, so later drilling results are not reflected in its economic projections.
Among results reported in October was an intercept of 37 metres grading 2.16 g/t gold, including 9 metres at 5.10 g/t. The intercept is an exploration result, not a new reserve, and would require further estimation and technical assessment before it could be incorporated into a mine plan. For now, the next regulatory step is the review of the lease application, followed—if granted—by the environmental authorization process.
More in Resources
Spartan Metals’ Victorio PEA sets US$683m initial cost, but estimates remain preliminary
A block-caving design underpins the New Mexico plan, while resource classification and metallurgy still need further testing.
Chile's peso comes under pressure as dollar reaches highest level since 2025
Miners may gain on peso-denominated costs, but the currency move coincides with weaker copper revenue.
Cabral Gold expands Cuiú Cuiú resource as inferred ounces dominate
Cuiú Cuiú’s first phase targets oxide ore, while much of the expanded inventory lies in primary rock requiring a different development route.