Marimaca Copper’s US$450m Sprott package clears committee, but remains conditional
The Antofagasta oxide project has a US$587 million initial build estimate, larger than the proposed financing package.

cruxinvestor.com
Why it matters: Committee approval advances financing for a proposed new cathode operation, but construction funding cannot be drawn until key conditions are met.
Up to US$450 million — a proposed package comprising a US$425 million credit facility and US$25 million in equity investment.
US$587 million — estimated initial investment for the Marimaca Oxide Deposit project.
50,000 tonnes a year — planned copper cathode output at steady-state operations over a projected 13-year mine life.
5.75% plus a benchmark rate — proposed annual interest rate, with the benchmark set at the greater of US SOFR and 2.75%.
Marimaca Copper’s subsidiary Compañía Minera Cielo Azul Limitada has received approval from the investment committee of Sprott Resource Lending for a proposed financing package of up to US$450 million for the Marimaca Oxide Deposit (MOD) in Chile’s Antofagasta Region. The approval is not a completed financing: legal and financial review, definitive agreements and other conditions remain outstanding.
The proposed package is US$137 million below the project’s estimated initial investment. Marimaca has not detailed in the disclosed information how it would fund the difference. The proposed US$425 million senior secured credit facility and US$25 million equity investment would support construction, commissioning, working capital and other corporate expenses.
Credit terms depend on final agreements
The credit facility would have a 7.5-year term and no copper-price hedging requirements or production-linked payments. Its proposed annual interest rate is variable at 5.75%, plus the greater of the US SOFR reference rate and 2.75%. Principal repayments would begin on March 31, 2031.
A first draw of US$100 million could be available after Marimaca makes a Final Investment Decision (FID) and satisfies the contractual conditions. The company has not yet announced that it has taken FID, and the proposed draw remains subject to completion of the financing process.
Mining permit enables early works
Marimaca said it received the Method of Mining sectoral permit from Chile’s National Geology and Mining Service (Sernageomin) on November 26. The authorization allows early works, including site preparation and earthmoving, and complements the project’s environmental approval, known as the Environmental Qualification Resolution, obtained in November 2025.
Company president Nico Cookson said Marimaca expects to accelerate detailed engineering, field activities and construction preparations in the coming months. The project is designed to produce 50,000 tonnes of copper cathodes annually once it reaches steady-state operation, with a projected 13-year mine life.
The company is also continuing exploration at Pampa Medina, where it has identified oxide and sulphide copper mineralization that it describes as high grade. Marimaca’s next financing steps are to complete Sprott’s legal and financial review, execute definitive agreements and meet the conditions required before deciding whether to proceed with the project.
More in Resources
US copper smelters face a widening gap as mines send concentrate overseas
Only two primary smelters remain as data-centre, grid and defence demand adds pressure to a chain already tied to overseas processors.
Pongkor flood rescue continues as authorities work to identify miners
Floodwater and mud from the Ciseureuh River entered two illegal shafts inside Antam’s mining area after heavy rain.
Cochilco sees Chile reaching 50 tonnes of gold, but rank gains hinge on rivals
Atacama operations are reshaping Chile’s gold output, but the country’s place in the global table also depends on other producers’ year-end totals.