Los Bronces water plan wins approval, but Vega Sur recovery hinges on flow separation
The design must keep contact water out of El Choclo while routing snowmelt toward a recovering high-altitude wetland.

Why it matters: The approval covers long-term management of potentially acidic drainage at an inactive waste-rock deposit while maintaining the water regime supporting Vega Sur’s passive recovery.
US$90 million — declared investment for the Donoso Norte project.
186 litres per second — planned pumping capacity for captured contact water.
1,000 m³ — capacity of the supplementary collection pool.
Up to 8 litres per second — maximum estimated freshwater flow for seasonal restitution to Vega Sur.
Anglo American Sur’s Donoso Norte water-management project at the Los Bronces mine in Chile received environmental approval on 20 November 2026. The US$90 million initiative is designed to capture water that has contacted the waste-rock deposit, divert clean snowmelt and maintain conditions at Vega Sur, near Laguna Donoso. The approval does not itself set a construction start date.
The project was submitted as an environmental impact study and covers works in the Donoso, Los Bronces and Confluencia sectors of the operation. The deposit has not been operating since 2009, according to the project file. Its 2004 environmental approval required temporary water management in response to acid drainage and called for a permanent solution later.
Contact water would be collected and pumped to a Los Bronces reservoir
For contact water that may emerge downstream of the deposit, the plan includes a cutoff wall to intercept subsurface flows, a supplementary 1,000 m³ collection pool and a pumping station rated at 186 litres per second. A pipeline would carry the captured water to a reservoir within Los Bronces.
The works would provide environmental approval for a permanent system that complements temporary infrastructure operating since 2015. The project’s stated aim is to prevent water from the deposit from flowing through the El Choclo micro-watershed. Contact water would be managed separately from non-contact water, rather than directed through the same system.
A diverted channel and seasonal flow are intended to support Vega Sur
For non-contact water, the project would divert and extend the deposit’s South Contour Channel, using both open and piped sections. The channel is intended to carry snowmelt from the southern slope of the El Choclo micro-watershed toward Vega Sur.
The plan also supplements a water-restitution system with a maximum estimated flow of 8 litres per second of fresh water. A pipeline would convey it from the Confluencia sector to Vega Sur during the summer and snowmelt period, between October and March. The project description presents the flow as a design measure to maintain conditions associated with the wetland’s passive recovery. In winter, Laguna Donoso sits at about 3,900 metres above sea level, where low temperatures and snow accumulation mean no flow requiring restitution is recorded.
The project file says the solution would replace fresh-water extraction with contact water from the Donoso sector while maintaining the water-volume balance in the Aconcagua River basin. It does not provide a construction timetable or commissioning date.
Environmental approval includes sectoral permits and a 30-day appeal period
The assessment includes sectoral permits covering mine-closure planning, water evacuation or treatment works, waste facilities including hazardous waste, channel modifications and defenses, and construction outside urban boundaries. The environmental approval is not, by itself, authorization of a construction start date.
The resolution may be challenged through an appeal in cases provided for under Chile’s Law 19,300. The project file gives a 30-day period from notification of the relevant environmental approval.
More in Resources
US resumes Russian palladium imports as Sibanye-Stillwater challenges tariff ruling
A steep Commerce Department rate has not become an import order, leaving the legal dispute over Russian metal unresolved.
EU cold-rolled steel duties reach Vietnam, with Chinese inputs under scrutiny
The investigation tested whether Chinese hot-rolled steel inputs altered Vietnam’s market conditions alongside a review of five exporting economies.
Codelco faces dust charges at Ministro Hales as Talabre case hinges on compliance
The SMA’s parallel proceedings target a crusher and waste dump at one operation, and groundwater and tailings controls at another.