COMIN’s Venus Marta mine enters Chile review without a plant of its own

Its 12-year extraction plan sits inside a 16-year project life, while the environmental filing remains at the admission stage.

COMIN’s Venus Marta mine enters Chile review without a plant of its own

Why it matters: Venus Marta’s production profile depends on third-party processing, while expected recoveries and final copper output remain unspecified.

By the numbers:
  • US$50 million — estimated investment for the project.

  • 21.6 million tonnes — planned ore extraction over 12 operating years.

  • 1.07% CuT — projected average total copper grade.

  • 75% / 25% — planned ore allocation between Atacama Kozan and ENAMI.

COMIN S.A. has filed its Venus Marta underground mine project with Chile’s Environmental Impact Assessment System (SEIA), proposing to extract 21.6 million tonnes of ore over 12 years near Tierra Amarilla. The US$50 million project has no processing plant of its own: ore is slated for treatment at Minera Atacama Kozan and ENAMI’s Manuel Antonio Matta plant. The environmental declaration, submitted on October 30, 2026, was at the admission stage.

A 12-year extraction plan within a 16-year project

The mine is planned for the Candelaria-Punta del Cobre district, about 8.5 kilometres southeast of Copiapó. COMIN’s design calls for extraction of 5,000 tonnes per day, or 150,000 tonnes per month and 1.8 million tonnes per year. The projected average grade is 1.07% total copper (CuT).

Applying that grade to the planned 21.6 million tonnes yields an arithmetic estimate of about 231,000 tonnes of contained copper in the ore. It is not a forecast of saleable copper: the amount recovered will depend on processing and metallurgical recoveries at the receiving plants, for which the available project details give no estimates.

The stated 16-year total project life includes construction, operation and closure; extraction is scheduled for 12 years, not the full 16. COMIN estimates a peak workforce of 145 people.

Ore handling relies on two external plants

Ore would be hauled from underground stopes by dump trucks and unloaded at a temporary surface stockpile with capacity for 12,000 cubic metres. The planned 5,000-tonne daily dispatch would take place during daytime hours. The proposed allocation sends 75% of the ore to Minera Atacama Kozan and the remaining 25% to ENAMI’s Manuel Antonio Matta plant.

The project’s infrastructure is therefore centred on mining and ore handling, with treatment dependent on two third-party facilities. The filing does not specify expected recoveries or final copper production.

COMIN estimates that construction and mining would generate about 1.08 million tonnes of waste rock. Two nearby dumps are planned: the North dump, with capacity for 360,000 tonnes, and the South dump, with capacity for 720,000 tonnes.

Environmental review follows an earlier termination

The company estimates that project execution could begin in March 2028, subject to the required environmental and sectoral approvals. The October 30 filing was still at the SEIA admission stage, before substantive environmental assessment.

Venus Marta’s previous environmental review ended early in 2023 because essential information was missing, according to the project account. The current proposal must proceed through the applicable approvals before the projected start date.