WEDNESDAY, NOVEMBER 25, 2026 · GLOBAL EDITION (EN) · EDICIÓN LATAM (ES)

Codelco’s Tocopilla water link enters final tests as two divisions face obligations

Codelco has not identified which divisions will receive the desalinated water, leaving the scale of the planned shift unclear.

Codelco’s Tocopilla water link enters final tests as two divisions face obligations

techint.com

Why it matters: The project could reduce Codelco Norte’s reliance on continental water, while environmental commitments are tied to the continuity of two divisions.

By the numbers:
  • Four divisions — Chuquicamata, Radomiro Tomic, Ministro Hales and Gabriela Mistral featured in the presentation.

  • 2027 — the year Codelco Operaciones Norte identified for its forward agenda.

  • Two divisions — Ministro Hales and Gabriela Mistral have environmental commitments to implement.

Codelco’s desalinated-water system from Tocopilla to the interior is in its final phase and undergoing tests, according to Fernando Promis, the company’s community affairs and sustainability manager for Operaciones Norte. The initiative is intended to supply Codelco divisions as the operation shifts away from continental water, but the company did not identify the recipients, expected volumes or start date.

The project and environmental measures were among the initiatives presented by Codelco Operaciones Norte at FECOP 2026, a contractors and suppliers fair organised by the Calama branch of the Chilean Chamber of Construction. The presentation covered work across Chuquicamata, Radomiro Tomic, Ministro Hales and Gabriela Mistral.

Tocopilla system remains in testing

Promis described the water transition as one of the operation’s challenges towards 2027. The system would transport desalinated water from Tocopilla to divisions farther inland. Codelco’s presentation placed the project in final-stage preparation and testing; it did not say that deliveries had begun or provide a commissioning schedule.

The company also did not quantify how much continental water the system is expected to replace. Without details on allocation, volume and timing, the scale of the transition for each division cannot yet be assessed. The stated objective is to supply Codelco divisions with desalinated water, but the information presented did not specify whether all four northern divisions would receive it.

Environmental measures tied to two operations

Codelco said Ministro Hales and Gabriela Mistral must implement commitments set out in environmental impact studies approved during 2026. The measures relate to communities, environmental care and employment opportunities, and are linked to the operational continuity of both divisions.

The presentation did not detail individual measures, implementation deadlines or associated employment figures. At Ministro Hales, community visits began in March 2026 under voluntary commitments for the Desarrollo Futuro DMH project, which was approved in January of that year. That programme is one example of local engagement, but the company did not say how it relates to the full set of commitments now due for implementation.

Local engagement and operating plans

At FECOP, Codelco also outlined initiatives on emissions and particulate-matter control, education, heritage, employment and local suppliers. Promis said the company planned to share its work through meetings with neighbourhood groups, communal associations, industrial associations and other local forums, in addition to trade fairs.

The presentation did not provide quantified targets or division-by-division results for those areas, so it offered no basis for comparing performance among the four operations. The next stated steps are to complete testing of the water system and implement the environmental and territorial measures for Ministro Hales and Gabriela Mistral; Codelco has not disclosed detailed schedules for either.