WEDNESDAY, NOVEMBER 25, 2026 · GLOBAL EDITION (EN) · EDICIÓN LATAM (ES)

Auren solar project targets Escondida, but grid exports remain undefined

The Antofagasta proposal pairs solar generation with batteries, but the filing does not state how long they can discharge.

Auren solar project targets Escondida, but grid exports remain undefined

redimin.cl

Why it matters: The proposal could add a dedicated power source for Escondida while retaining an undefined route to Chile’s national grid.

By the numbers:
  • 35 MWac — planned solar generation capacity

  • 35 MW — battery system power capacity; energy storage capacity is not stated

  • US$61 million — investment recorded in the environmental filing

  • 21 years and five months — projected operating life

Auren has entered Chile’s Environmental Impact Assessment System (SEIA) with a declaration of environmental impact for a solar plant and battery energy storage system in the commune of Antofagasta. The project is intended to supply electricity to Minera Escondida, but its filing also allows for power to be injected into the National Electric System if required. The application is listed as “Under Admission”; no environmental approval is reported.

Supply route runs to Escondida’s Sulfuros 1 substation

The design combines solar modules on tracking structures with lithium-ion batteries. The batteries would store electricity generated during periods of high solar irradiation and deliver it when generation is lower or demand is higher. The filing gives the battery system’s power rating as 35 MW, but does not specify its energy capacity in megawatt-hours or its discharge duration.

Two 13.8 kV medium-voltage lines, measuring 5.7 kilometres, would carry electricity to Minera Escondida’s Sulfuros 1 substation. The mine is the stated priority for the power supply. However, the project description also provides for possible exports to the National Electric System and does not identify the conditions that would trigger them or the share of generation that might be allocated to the grid.

The proposed works include the solar park, battery system and civil, electrical and support infrastructure for operation and maintenance. The stated objective is to contribute to the security and resilience of Escondida’s electricity supply.

Application remains at an early assessment stage

The filing identifies Parque Artemis II SpA as the project holder and says the initiative corresponds to Sungrow Power Chile through that company. The project company would develop, build, operate and manage the facility, with administration and operations independent of the energy customer. It would also assume the applicable environmental and regulatory obligations. Gestión Ambiental Consultores SpA is named as the environmental consultant.

The proposal was submitted as a generating plant above 3 MW, under category c) of the SEIA regulations. The filing describes Auren as a new project, rather than one submitted in response to a regulatory order, a Superintendence of the Environment compliance programme or a court ruling. Its current admission status is an initial procedural stage; the available record does not report a favourable environmental decision.