CMPC completes US$670 million Guaíba overhaul with two distinct line bets
The work paired an expansion on one line with a separate upgrade whose payoff is harder to measure in tonnes.

valmet.com
Why it matters: Guaíba’s upgrade delivers two distinct operating gains: higher nameplate output on one line and lower production costs on the other.
More than US$670 million — combined investment in the two Guaíba projects.
350,000 tonnes a year — added capacity on Line 2.
21% — reported reduction in Line 1 production costs.
More than US$1 billion — CMPC’s planned investment for 2025–2026.
CMPC has completed a modernization of its Guaíba pulp mill in Rio Grande do Sul, Brazil, combining a capacity expansion on Line 2 with an upgrade to Line 1. The company said the projects involved more than US$670 million in investment; the reported production gains differ by line, with added annual capacity on Line 2 and lower production costs on Line 1.
BioCMPC adds capacity to Line 2
Launched in 2022, BioCMPC accounted for more than US$540 million of investment and increased Line 2’s annual capacity from 1.5 million to 1.85 million tonnes. The 350,000-tonne increase is more than 18% of the line’s previous capacity.
The work included a new recovery boiler and upgrades to the fibre line, alongside improvements to wood preparation, cooking, bleaching, drying and evaporation systems. The scope covered several stages of pulp production, from processing the raw material through to drying the finished pulp.
CMPC also said BioCMPC helped reduce carbon dioxide emissions, water consumption and effluent volumes. It did not provide figures for those changes, so their scale cannot be assessed from the reported data.
Revamp targets Line 1 costs
Announced in 2023, Revamp involved US$132 million in work on Line 1. The project covered the recovery boiler, chlor-alkali plant, electrical systems, automation and chemical processes. CMPC reported that the upgrades reduced the line’s production costs by 21%, but did not specify a monetary baseline or the resulting savings.
The two projects therefore have different reported measures of performance: BioCMPC increased nameplate capacity, while Revamp lowered production costs. CMPC chief executive Francisco Ruiz-Tagle said the investments were intended to improve efficiency and competitiveness, increase capacity, optimize operations and reduce costs. Felipe Alcalde, the company’s vice-president of pulp and boxboard industrial operations, described Brazil as a strategic market and Guaíba as a key pulp operation. The company’s broader claims about technology and resource use were not accompanied by additional quantified performance data.
Further investment planned for 2025–2026
Guaíba’s modernization forms part of CMPC’s investment plan of more than US$1 billion for 2025–2026. The company identified US$72 million for Remanufactura Los Ángeles, US$20 million for the Mulchén sawmill, US$41 million for the Santa Fe pulp mill and US$26 million for the Pacífico mill. Those named allocations total US$159 million; the company did not detail the distribution of the remainder of the plan in the figures provided.
More in Resources
Peru’s artisanal miners contest Reinfo deadline as strike threat grows
More than 9,000 rallied in Puno, while the proposed replacement law faces objections from alluvial miners.
Cajamarca’s copper pipeline tops US$16 billion, but production remains elusive
Michiquillay’s original 2016 start-up target has receded, leaving the region’s broader build-out dependent on projects yet to advance.
Chile mining deaths put contractor safety and chronic disease in focus
Contractors, transport workers and service providers share the operating chain, while some occupational harm can take years to detect.