Glencore signs 100,000-tonne lithium deal as Empower scales Texas project

Empower is still moving from early product testing toward commercial production, with its first sales targeted for 2027.

Glencore signs 100,000-tonne lithium deal as Empower scales Texas project

Why it matters: Glencore’s offtake gives a pre-production US lithium developer a prospective buyer, but the project must scale well beyond its initial modular unit.

By the numbers:
  • Up to 100,000 tonnes — battery-grade lithium carbonate covered by the 10-year agreement

  • More than 24,000 hectares — area covered by Project Summit in Texas

  • 250 tonnes per year — planned capacity of Empower’s first modular production unit

  • 99.68%–99.91% — purity reported for carbonate produced in five processing campaigns

Empower EIT has signed a binding 10-year supply agreement with Glencore for up to 100,000 tonnes of battery-grade lithium carbonate from its planned US operations. Empower is developing Project Summit in Texas and targets its first commercial sales in 2027, but has yet to begin production at commercial scale.

The agreement is intended to give the developer a buyer ahead of commercial output. Empower said supply would be directed primarily to the US government and commercial customers in the country, supporting domestic critical-mineral supply. The companies did not disclose a delivery schedule, annual volumes or pricing terms, so the maximum contract quantity does not establish how much product will be supplied in any given year.

Contract volume sets a scale-up challenge

The agreement’s maximum volume averages 10,000 tonnes a year over its 10-year term. That is twice the 5,000-tonne-per-year capacity Empower has described for a planned commercial facility. The comparison is an implied annual average, not a published delivery commitment: actual shipments could be lower or vary over the contract period, and the terms were not provided.

Empower’s nearer-term plan is to drill its first production wells and install a modular unit designed for 250 tonnes a year. The company has also outlined expansion to 5,000 tonnes annually. In April 2026, it submitted technical documentation to the US Department of Energy for development of a commercial facility at that scale.

Project Summit covers more than 24,000 hectares in Texas. The company has not provided a production start date for the larger facility in the information available, leaving the pace and funding of the step-up from the initial unit as key execution factors.

DLE route and product testing

Empower plans to use its EmTECH Powered by LiMAX platform, which combines direct lithium extraction (DLE) with conversion into battery-grade lithium carbonate. The company says the approach brings extraction and downstream processing within one operating structure.

In July 2026, Empower reported producing lithium carbonate at its Dallas operations and innovation centre. Third-party assays cited by the company returned purity results from 99.68% to 99.91% across five processing campaigns. Those results demonstrate product testing, but do not establish commercial-scale operating performance or output.

The company also announced Tom Currier, chief executive of electrical-equipment manufacturer Maverick Power, as a strategic investor and board member. Empower did not disclose the investment amount or the ownership stake acquired.

The next operational steps identified by Empower are drilling the initial production wells and starting the 250-tonne-per-year modular unit, while the larger facility remains subject to development and scale-up.