Ora Banda targets 300,000 ounces at Davyhurst as a new plant takes shape

Riverina and Sand King are supplying the current base, but the next production step rests on mines still being developed.

Ora Banda targets 300,000 ounces at Davyhurst as a new plant takes shape

orabandamining.com.au

Why it matters: Davyhurst’s ramp depends on bringing new underground mines online while expanding processing capacity beyond the current mill.

By the numbers:
  • About 141,000 ounces — Ora Banda’s record FY26 production, including third-party processing.

  • 4.2 million tonnes a year — planned combined capacity of the existing and new plants.

  • $75 million — exploration budget for FY27, which the company expects to repeat in FY28 and FY29.

  • 3.69 million ounces — Davyhurst resources after more than doubling since FY23, according to Ora Banda.

Ora Banda is targeting annual gold production of 300,000 ounces at Davyhurst by FY29, with growth expected from new mines, exploration and a second processing plant. The company reported record production of about 141,000 ounces in FY26, up 53% year on year; that total included 34,300 ounces of attributable equivalent production processed at third-party facilities.

Riverina and Sand King are the current operating base. Ora Banda reported FY26 production of about 66,000 ounces from Riverina and 78,000 ounces from Sand King. It is developing Waihi as a third underground operation and preparing Round Dam as a potential fourth source of ore. The ramp therefore depends not only on mine development, but also on delivering the planned processing expansion.

New mines are central to the FY29 target

Waihi, about three kilometres from the existing plant, has a resource of 480,000 ounces and reserves of 101,000 ounces. Its Golden Pole vein contributes about 41,000 ounces to reserves at a grade of 5.0 grams of gold per tonne. Ora Banda expects first ore from Waihi in mid-2027 and plans to prioritise its processing at the current facility while gradually reducing reliance on third-party plants.

Round Dam’s prefeasibility study estimates production of 724,000 ounces over eight years. The company is targeting a start to mining in 2028, subject to a final investment decision it expects to make next year. That decision remains a condition for the project to join Davyhurst’s ore supply.

Riverina produced about 66,000 ounces in FY26 and has a resource of 828,000 ounces, including reserves of 100,000 ounces at 3.5 grams per tonne. Sand King produced about 78,000 ounces. Its resource stands at 524,000 ounces, with reserves of 125,000 ounces; Ora Banda’s stated aim is to sustain annual production of about 100,000 ounces from the mine.

Second plant would lift Davyhurst capacity to 4.2Mt

The new plant is being built beside the existing mill, which has annual capacity of 1.2 million tonnes. The second facility is designed to process 3.0 million tonnes a year, bringing the site’s planned combined capacity to 4.2 million tonnes. Ora Banda has budgeted $375 million for the project and expects commissioning to begin in the quarter ending March 2028.

The company formalised a A$233 million engineering, procurement and construction contract with GR Engineering in June 2026, after selecting the contractor as preferred in May. The additional capacity is intended to handle ore from Riverina, Sand King, Waihi and Round Dam, while reducing reliance on a single plant and third-party processing. Those benefits depend on the new facility being completed and performing as planned.

Ora Banda also plans $180 million of infrastructure spending through FY29, including expanded accommodation, an all-weather airstrip, haul-road upgrades and an on-site laboratory. It expects to fund its growth from available resources and future cash flows, alongside an unused $300 million revolving credit facility. At the September-quarter close, it reported liquidity of about $507 million, including $208 million in cash.

Exploration targets resource growth across Davyhurst

Ora Banda plans to spend $75 million on exploration in FY27 and expects a similar budget in each of the following two financial years. Since FY23, the company says it has more than doubled Davyhurst’s resources to 3.69 million ounces and increased reserves by about 281% to 610,000 ounces. Its tenements cover 1,140 square kilometres across more than 130 kilometres of prospective greenstone belt.

At Little Gem, a resource estimate is expected by the end of this year or early 2027. Recent drilling extended mineralisation over more than 2.6 kilometres of strike and to 750 metres depth; reported intersections include 6 metres at 13.3 grams per tonne, 8.8 metres at 6.3 grams per tonne and 2 metres at 44.3 grams per tonne. Ora Banda is also drilling at Waihi, where reported results include 11.5 metres at 26.0 grams per tonne and 1.6 metres at 65.9 grams per tonne at the Midnight prospect. The company’s next resource estimate at Little Gem and the planned investment decision for Round Dam are among the steps still ahead of the FY29 production target.