NRW named preferred contractor at Bullabulling as Minerals 260’s investment decision looms
Early services are set to start before full mobilisation, while Bullabulling’s production target remains a year away.

argonaut.com
Why it matters: Bullabulling’s planned development now has a preferred mining contractor, but the long-term services agreement depends on Minerals 260 approving the project.
A$1 billion — estimated value of the first five years of services, not a finalized contract
2027 — Minerals 260’s expected year for its final investment decision and the planned start of mining
2028 — Bullabulling’s target year for first production
NRW Holdings has been selected as preferred mining contractor for the Bullabulling gold project in Western Australia, with initial services expected to begin immediately. The long-term contract remains subject to a final investment decision (FID) by Minerals 260, expected in early 2027.
The proposed agreement covers five years of services, with an option to extend. NRW estimates the work at close to A$1 billion over that initial term, equivalent to about US$664 million. The estimate is for the planned services; it is not the value of a finalized long-term contract. The definitive agreement is expected to be signed after Minerals 260 makes its investment decision.
Mining is planned to start before first production
Bullabulling Operations Pty Ltd, a subsidiary of Minerals 260, is targeting first production in 2028. The current schedule envisages mining starting in the December 2027 quarter, ahead of that production target. Full site mobilisation is planned for the September 2027 quarter, with mining activities due to follow in the next quarter.
The early appointment allows preparatory services to proceed before full mobilisation, but the key development milestones remain planned rather than completed. The FID is the condition for finalizing the long-term contract. In September 2026, Franco-Nevada committed a further A$200 million to Bullabulling, bringing financing announced for the project that year to A$420 million.
Scope spans site preparation to ore haulage
The work is expected to include site preparation, pre-stripping, dewatering, loading and haulage, drilling and blasting, and ancillary services. NRW subsidiary Action Drill & Blast Pty Ltd will carry out the drilling and blasting component.
NRW plans to meet a substantial portion of equipment requirements with its own machinery that is currently idle. Fleet development and the ramp-up in operations are expected to occur in stages over the first three years. The company has not specified the number of units involved or the pace at which they would be deployed.
NRW’s capital spending is phased
NRW estimates it will deploy about A$20 million in new capital in fiscal 2028, rising to approximately A$80 million from the third year. Those figures represent capital NRW expects to commit to delivering the services; they are separate from the estimated value of the five-year agreement.
The next major contractual step is Minerals 260’s FID, expected in early 2027. Until that decision, initial services may proceed, but the definitive long-term agreement remains pending.
More in Resources
Chile litigation covers 43% of major-project investment, versus 24% of projects
Most original decisions are upheld, but appeals can pass through several bodies and take years to resolve.
LGMG debuts VTH150 electric mine truck, but operating data remain undisclosed
Its permanent-magnet wheel-drive system is the centerpiece; the test is whether LGMG can take the design from claim to full-scale fleet use.
Multotec's closed slurry launders target high-tonnage plants, but flow hinges on design
Gravity transfer removes an extra pumping step, but each line must be tailored to the slurry it carries.