Kantra advances Coburn study as rail haulage costs remain under review

The plan would send Coburn ore to Kanmantoo’s existing plant, but the proposed rail route still needs a firmer cost basis.

Kantra advances Coburn study as rail haulage costs remain under review

Why it matters: Using Kanmantoo’s existing plant could shape Coburn’s infrastructure needs, but the transport and processing assumptions are not yet final.

By the numbers:
  • 5–7 cents per tonne-kilometre — preliminary transport cost range to be reviewed in the next study phase.

  • More than 90% copper recovery — achieved in composite metallurgical tests using Kanmantoo’s flowsheet and reagents.

  • 18 months — further pre-feasibility work planned before an investment decision.

  • A$18.5–19.5 million — Kantra’s 2026 major capital expenditure guidance, including planned second-phase work.

Kantra Copper’s board has approved the second phase of pre-feasibility work for the Coburn project, following initial logistics studies and metallurgical tests that support assessing the use of the existing Kanmantoo processing plant in South Australia. The proposed route would move ore from Coburn to a rail siding near Cockburn, then by train to Kanmantoo. The company estimates transport at 5–7 cents per tonne-kilometre, but said the figure comes from first-phase work and will be reviewed; it is not a definitive project estimate.

Rail route and plant configuration remain under study

The concept includes a proposed siding about 20 kilometres from Coburn, alongside an access-road corridor. At Kanmantoo, the design includes a separate siding and rail loop beside the plant. Both the route and the processing configuration require further analysis in the second phase.

The approach would use existing processing infrastructure rather than a standalone plant at Coburn. Its viability depends on defining a transport solution and a plant configuration suited to the project’s ore. Kantra said further optimisation and variability testing are still required to establish processing assumptions.

Composite metallurgical tests completed in October 2026 recorded copper recoveries of more than 90% and gold recoveries of more than 50% using Kanmantoo’s flowsheet and reagents. The results support further evaluation of processing Coburn material at the facility, but do not settle the final plant design. Managing director Bob Fulker linked the metallurgical and logistics work to the board’s decision to advance the study.

Study spending and fieldwork expand in phase two

Kantra estimates total pre-feasibility spending for Coburn at A$11 million to A$13 million. It had spent A$970,000 by the end of October 2026. The company raised its 2026 major capital expenditure guidance to A$18.5 million–A$19.5 million to include expected second-phase spending.

The next phase is set to cover geology, mine design, processing, infrastructure, logistics, permitting and project economics. Kantra has also started drilling at Coburn. The first eight holes were designed to support metallurgical testing, geochemical characterisation and validation of geological domains; six holes totalling 1,318 metres had been completed by 20 November.

After that verification programme, drilling is intended to improve geological confidence for later studies. The company also plans to assess resource-extension opportunities in 2027. A surface electromagnetic survey has been completed to help identify the mineralised structure at depth and along strike, but its results still need to be processed and interpreted before they can guide further targets and drill designs.

Ownership and investment decision remain conditional

Coburn is subject to a staged earn-in agreement with Havilah Resources. Kantra could earn an 80% interest, subject to spending commitments, a final investment decision and other transaction requirements. Advancing the pre-feasibility study does not itself satisfy those conditions or approve construction.

Kantra expects another 18 months of pre-feasibility work before making a final investment decision. In the meantime, it says it remains focused on meeting its 2026 production and cost guidance at Kanmantoo. The proposed rail arrangement, processing configuration and transport estimate will require further work as the study progresses.