CuFe links Orlando and Gecko, but Tennant Creek’s early-feed option remains unproven

A combined development study is nearing completion, while historic mine dumps could offer an earlier processing route if their material proves suitable.

CuFe links Orlando and Gecko, but Tennant Creek’s early-feed option remains unproven

ntnews.com.au

Why it matters: The integrated study will test whether adding Gecko changes the development case for CuFe’s Orlando project, while dump material could offer a separate route to earlier processing.

By the numbers:
  • 55% — CuFe’s current interest in the project; it has a conditional agreement to acquire the remaining 45%.

  • Before the end of 2026 — CuFe’s expected publication window for the integrated study.

  • Early 2027 — the planned timing for an independent review and JORC resource update at Orlando.

CuFe is finalising a study that combines the Orlando and Gecko deposits in a development plan for its copper-gold project in Tennant Creek, Australia’s Northern Territory. Planning and cost work for Gecko is complete, but financial modelling remains underway to determine how including the neighbouring deposit changes Orlando’s development case. CuFe expects to publish the study before the end of 2026.

The company is also assessing whether material in historic mine dumps at Orlando and Gecko could provide feed to a concentrator before full development of the deposits. The dumps’ volume and grade have not been established, and CuFe is seeking approval to drill or excavate trenches to characterise them.

Gecko’s costs are set; integrated economics are pending

In May, CuFe outlined an Orlando development case involving both open-pit and underground mining. The new study will incorporate Gecko and assess the effect on the combined plan. CuFe owns 55% of the project and has signed a conditional agreement to acquire the other 45%; it has not yet secured full ownership.

Some processing assumptions will draw on technical work by the Tennant Creek Copper Alliance (TCCA), established in October 2024 by CuFe, Emmerson Resources and Tennant Minerals. Pan African subsequently acquired Emmerson. The alliance is studying a multi-user processing plant for the district. Engineering and cost work is complete, with the final report being prepared. Its capital and operating cost estimates are expected to inform CuFe’s integrated study. The company has also said the plant design and process flowsheet could guide a standalone development option.

CuFe, the Australian government and the Northern Territory government jointly funded the alliance’s plant study.

Drilling and geophysics will inform resource work

Initial reverse-circulation drill samples are at the laboratory, with assays expected in December. The campaign is moving from infill and extension work at Orlando to exploration targets along the Gecko trend. After a mobilisation delay, CuFe secured a replacement diamond rig to collect core for metallurgical, geotechnical and waste-characterisation studies.

A helicopter-borne magnetotelluric survey is measuring subsurface resistivity to rank and prioritise targets for 2027 drilling. At Orlando, CuFe is also reviewing the boundaries of mineralised zones to assess whether continuity extends beyond the current model. An independent consultant is due to review the interpretation and prepare a JORC resource update in early 2027; the company plans to test the same approach at Gecko afterward.

Historic dumps need testing before they can supply feed

The company is examining material at Orlando and Gecko that was below the cut-off grades used by previous operators. If suitable, it could be crushed, sorted and separated for sale as feed to a concentrator ahead of full deposit development. The option depends on establishing the dumps’ tonnage and grades, which are currently unknown.

CuFe is working with environmental consultants to seek permission for drilling or trenching. The district has a precedent at Nobles, a gold operation run by Tennant Mines that began with higher-grade material from historic dumps. That example does not establish that Orlando and Gecko’s dumps have comparable characteristics. Tennant Mines is separately studying potential copper production at Warrego and other nearby deposits.