Centinela’s US$4.4bn expansion nears start-up as gold takes a larger role
Esperanza Sur is first in the feed sequence, while Antofagasta Minerals is already assessing a larger processing phase.

im-mining.com
Why it matters: The expansion is designed to lift copper output, but the projected value of its additional gold could be comparable to the project’s capital cost.
US$4.4 billion — approved investment for the Centinela expansion.
More than 90% — reported construction progress.
10 years — period cited for the projected additional gold output.
More than 50% — potential increase in processing capacity under a second phase.
Antofagasta Minerals’ Centinela expansion in Chile is more than 90% complete, with the plant nearing start-up. The company says the additional gold expected from the project over 10 years could have a value sufficient to cover its US$4.4 billion investment, although it has not disclosed the production volumes or price assumptions behind that estimate.
The project was designed to increase copper production. The gold estimate adds a potentially material by-product contribution, but the available details do not establish whether the comparison is based on gross revenue or another measure. It should therefore be read as a project estimate, not as a demonstrated return or a forecast of net cash flow.
Esperanza Sur leads the plant’s feed sequence
The new plant is expected to receive ore from two open pits in stages. Feed will begin with Esperanza Sur, with Encuentro Sulfuros scheduled to be incorporated later. That makes the first deposit central to the facility’s start-up, while the second is part of the planned supply sequence.
Construction of Encuentro Sulfuros began in August 2025. The project’s first blast removed more than 450,000 tonnes of material. The wider expansion is being built in Sierra Gorda and is the largest investment in Antofagasta Minerals’ history.
Antofagasta Minerals already produces gold from its copper operations at Los Pelambres and Centinela. The company’s comparison is between the additional gold projected from the expansion and the mines’ combined gold production in 2025: the projected increment is more than half that combined total. No absolute production figures were provided, so the incremental volume and its precise share cannot be calculated.
A larger processing phase remains under study
As the first phase approaches start-up, Antofagasta Minerals is assessing a second phase that could increase processing capacity by more than 50%. The proposal remains under evaluation; the company has not disclosed a final capacity, investment decision or schedule.
For now, the approved expansion is the project moving toward operation, with Esperanza Sur first in the feed plan and Encuentro Sulfuros to follow. In November 2025, Antofagasta Minerals said Nueva Centinela was progressing on schedule and within budget. The gold valuation remains difficult to assess independently because the company has not detailed the volumes, prices or economic measure used in its comparison with the investment.
More in Resources
Epic Gold defines Wilson and Fenton resources, but mine economics remain unproven
Cartier Resources retains royalties on both Quebec properties, while inferred classification and undisclosed terms limit what the figures can establish.
CuFe links Orlando and Gecko, but Tennant Creek’s early-feed option remains unproven
A combined development study is nearing completion, while historic mine dumps could offer an earlier processing route if their material proves suitable.
Gold miners outpace bullion in rebound after metal’s steepest weekly fall since March
The reversal puts the cost structure behind producer shares back in focus, while recent losses show the trade has not been uniform.