Trafigura injects US$11.76m into La Farola owner as court challenge persists
A Colla community is contesting the environmental review of the Tierra Amarilla project, with the case still under consideration.

Why it matters: Trafigura’s capital injections strengthen the company developing La Farola, while the project’s environmental review remains under challenge.
US$11.76 million — total cash capital increases subscribed by Trafigura Ventures V B.V.
US$38.76 million — Minera Altair’s share capital after the increases, up from US$27.00 million.
US$260 million — planned investment in the La Farola project.
90,000 tonnes a year — planned copper concentrate production over a 15-year operating life.
Trafigura made two cash capital increases totalling US$11.76 million in Minera Altair, the Chilean company developing the La Farola copper-gold project in the Atacama Region. The increases, formalised in July and September 2026, lifted Altair’s share capital to US$38,761,818 from US$27,001,818, according to documents published in Chile’s Official Gazette.
Trafigura Ventures V B.V. subscribed and paid for all the new shares in cash. The first increase, approved at an extraordinary shareholders’ meeting on July 7, issued 406 shares for US$5.8 million. A second increase, approved on September 1, issued another 417 shares for US$5.96 million.
Capital followed Trafigura’s move to full ownership
Trafigura had acquired the remaining 50% of Minera Altair that it did not already own, giving it full control of the company, according to the group’s financial statements for the half-year ended March 31, 2026. Altair announced the ownership change publicly on November 16, alongside management appointments.
Rolando Cubillos was named general manager, while Juan Cantador took responsibility for executing the La Farola project. The company said it would maintain its environmental and social commitments to local communities and authorities.
La Farola plans a 15,000-tonne-a-day operation
Located in the commune of Tierra Amarilla, La Farola is planned as an open-pit mine with a mineral-processing plant and filtered tailings storage facility. Minera Altair’s plans call for processing capacity of 15,000 tonnes of ore a day and annual production of 90,000 tonnes of copper concentrate containing gold over 15 years.
The company estimates the project could create up to 1,200 jobs during construction and 600 during operations. These are projections; the available project information does not provide a construction schedule or a production start date.
Colla community’s challenge remains before the court
La Farola received a favourable environmental assessment on March 31, 2025. The Colla Tata Inti community of Pueblo de Los Loros later challenged the assessment before Chile’s First Environmental Court, raising concerns about the evaluation of atmospheric impacts, potential risks to public health and the absence of Indigenous consultation.
At arguments reported by the court on August 3, 2026, both the Environmental Assessment Service and Minera Altair asked the court to reject the claim, arguing that the community lies outside the project’s area of influence. The case remained under consideration after the hearing; no ruling is reported in the available information.
More in Mining Stocks
Gold rebound lifts Sibanye, AngloGold and Newmont after a week of pressure
Bullion had just posted its steepest weekly fall since March, while the morning’s share gains offer no clean read on what drove each stock.
Matías Lagos takes charge of Chile’s mining pilot centre in its third phase
The CNP wants to bridge technology validation and mine-site use, but it has not disclosed the initiatives or targets for this next stage.