Nyankanga's proposed paste-backfill plant could open access to higher-grade ore, but its schedule still rests on feasibility work.

Perenti secures five more years at Geita as AngloGold weighs output expansion

Why it matters: The contract secures Perenti's underground work at Geita while AngloGold Ashanti assesses whether new infrastructure can support higher production.

By the numbers:
  • About $1 billion — stated value of the contract extension

  • 31 October 2031 — new contract end date

  • 600,000 ounces a year — Geita production target, compared with 492,000 ounces in 2025

  • 3 million tonnes a year — proposed capacity of a new processing line

Perenti has secured a five-year extension to provide underground mining services at the Geita gold mine in Tanzania, under an agreement valued at about $1 billion. The contract with Geita Gold Mining, an AngloGold Ashanti subsidiary, runs through 31 October 2031 and covers mine development, production and associated services.

Work will continue through AUMS Geofields Tanzania, a joint venture in which African Underground Mining Services and other Perenti subsidiaries hold a combined 80% interest. Tanzanian partner Geofields owns the remaining 20%. Perenti said the extension continues a relationship with AngloGold Ashanti at Geita that has lasted more than a decade.

Geita's production plan depends on feasibility work

The contract extension comes as AngloGold evaluates a paste-backfill plant for the Nyankanga underground mine. The proposed system would fill mined-out areas, potentially allowing access to higher-grade ore. Commissioning is planned for the first quarter of 2028, subject to feasibility studies.

The backfill plant is part of a broader plan to raise Geita's annual output to about 600,000 ounces, from 492,000 ounces in 2025. AngloGold is also considering a processing line with capacity of 3 million tonnes a year to treat additional open-pit ore and low-grade stockpiles. That line is envisaged to start up in late 2029 or early 2030.

Perenti's contract award is not conditional on approval or construction of either expansion initiative. The extension therefore secures the contractor's underground role while AngloGold's proposed production measures remain under study.

Joint venture structure meets Tanzania's local-content rules

Changes to Tanzania's local-content rules in 2025 require non-indigenous suppliers covered by the joint-venture provision to partner with a wholly Tanzanian-owned company operating in the same sector. The local partner must hold at least a 20% interest. Geofields' stake in AUMS Geofields Tanzania meets that minimum, according to the terms outlined for the venture.

Perenti said the contract requires about $22 million in capital in fiscal 2027, an amount already included in its financial projections. The company also reported that it met its guidance for a fifth consecutive year in fiscal 2026, with underlying revenue of about $3.5 billion, record underlying earnings before interest, tax and amortisation of $340 million, and adjusted free cash flow of $182 million.

Perenti shares had fallen 40.5% in 2026 as of 20 November on the Australian Securities Exchange. Chief executive Vanessa Torres said the award reflected continuity in the relationship with AngloGold Ashanti, while contract-mining president Gabrielle Iwanow pointed to the Geita teams' accumulated experience and the partnership with Geofields. Perenti said the local partnership supports employment and workforce training opportunities. The next stated milestone for the proposed Nyankanga backfill system is completion of the feasibility work underpinning its planned 2028 start-up.