Troilus orders Metso equipment as Quebec mine redevelopment moves into engineering
The order covers the plant’s core size-reduction circuit, while the companies are still working out how far support will extend beyond delivery.

Troilus orders Metso equipment as Quebec mine redevelopment moves into engineering
Why it matters: The equipment order advances planning for a mine redevelopment whose processing plant will need to handle crushing, grinding and screening at scale.
2 million ounces of gold — produced at the Troilus mine between 1996 and 2010.
Almost 70,000 tonnes of copper — produced over the same period.
US$850 million — debt commitment secured for the redevelopment in September.
Troilus Mining (TSX: TLG) has ordered crushing, grinding and screening equipment from Metso (HEL: METSO) for its Troilus gold-copper project in Quebec, bringing the supplier into the project’s engineering program as redevelopment planning advances.
The order includes a Superior MKIII primary gyratory crusher, Nordberg MP1250 cone crushers, apron and belt feeders, HRCe high-pressure grinding rolls, and ball mills with metallic mill linings. It also covers Grande Series Multi Flow wet and dry screens. Metso said the delivery will be the first delivery of these screens in North America.
Metso equipment enters project engineering
Metso will take part in technical workshops covering equipment interfaces, plant layout, 3D modelling and construction planning. The work is intended to address how equipment fits into the plant and its construction plan.
Troilus CEO Justin Reid said Metso’s technical offering and service capabilities in Quebec and across Canada made it a fit for the project. He said bringing an original equipment manufacturer into engineering at this stage could help address equipment interfaces early and support schedule and execution planning.
Metso North and Central America president Giuseppe Campanelli said the company’s technology portfolio, lifecycle services and Canadian presence positioned it to support project execution and future operations.
Broader lifecycle support remains under discussion
The companies are also planning a broader Life Cycle Services framework. Potential areas include commissioning, ramp-up support, technical services, training and spare-parts planning.
Located northeast of Quebec’s Val-d’Or district, the Troilus mine produced 2 million ounces of gold and almost 70,000 tonnes of copper from 1996 to 2010. Troilus secured a US$850 million debt commitment for the redevelopment in September. Metso is participating in the engineering program, while the broader service framework remains in the planning stage.
More in Resources
Guinea jails 202 alleged miners as Siguiri crackdown reaches former officials
Guinea’s effort to protect Siguiri’s rivers and farmland now extends beyond miners, while livelihoods tied to artisanal gold remain at stake.
Ranking: The Countries Offering the Highest Salaries in Mining
A cross-country salary comparison looks straightforward until one benchmark rests on a professional group of just 73 workers.