El Domo’s ball-mill components reach Ecuador, but installation is still ahead
Silvercorp’s November 2027 production target depends on site work the company has identified as a potential source of delay.

silvercorpmetals.com
Why it matters: El Domo’s equipment delivery advances construction, but the remaining installation work and site risks stand between the project and its production target.
US$90.9 million — Silvercorp’s construction spending as of September 30, 2026
US$298.2 million — updated project construction budget
November 2027 — targeted start of production
25% — Salazar Resources’ interest, funded through commercial production
Silvercorp Metals’ Curipamba-El Domo copper-gold project in Ecuador has received its first batch of major plant equipment at a domestic port, including components for the ball mill. The equipment has not yet reached the mine site; transport, installation and commissioning remain outstanding.
The delivery marks progress on the project, but does not confirm that the plant is ready to operate. Silvercorp is targeting production in November 2027 and has cautioned that the schedule depends, among other factors, on weather and contractor performance.
Ball-mill delivery leaves transport and installation ahead
Images shared by Salazar Resources show the mill shell at the port, alongside plant foundations and buildings under construction at the site. Salazar attributed the photographs to Silvercorp. The mill is a long-lead item that must be ordered well before installation, according to Salazar’s description of the equipment.
The next physical steps are delivery to the site, assembly and commissioning. Silvercorp has identified the tailings storage facility and the non-contact water diversion channel as the main potential delay points within the site-preparation package. The company has said it cannot assure that production will begin on its target date.
As of September 30, Silvercorp had spent US$90.9 million against an updated construction budget of US$298.2 million. It also reported US$383.7 million in cash, cash equivalents and short-term investments at that date. The cash figure is company-reported and does not, by itself, establish how much is allocated to El Domo.
Salazar’s interest is funded through commercial production
Salazar retains a 25% interest in El Domo and says its share is funded until commercial production. The company says it has no current additional funding obligations for the project’s development or construction, allowing it to direct capital to exploration while Silvercorp advances the build.
An updated technical report in July 2026 increased the project’s after-tax net present value by 121% to US$573 million, using an 8% discount rate. That valuation is distinct from construction spending and does not resolve the outstanding schedule and execution risks.
Salazar closed a C$3.5 million private placement on October 8 to fund drilling at Tarqui, where work is under way on the Yumi veins. The company expects to report initial results in the coming weeks. Salazar’s construction update was presented in paid promotional content approved by the company; project spending, schedule and funding details cited here are company-reported. The next construction step for the mill is its transfer from the port to the El Domo site.
More in Resources
China's Argentine mineral purchases top US by 47.5%, but Swiss lead
Lithium's expanding share is changing the export map, with Argentina's northwest increasingly central to the trade shift.
West Wits takes Qala Shallows to investors before stoping begins in 2027
The South African mine has poured gold from development ore, but its planned stoping phase is still months away.
Copper falls in London as tech selling and US tariff risks weigh on prices
Last week’s 10.13% loss has sharpened the contrast between tight metal availability in China and weakening investor appetite.