Colombia lifts restrictions on 15 mining areas, but Quebradón still faces a permit hurdle

The policy shift is intended to revive mining investment after foreign inflows fell sharply, as AngloGold Ashanti advances its Jericó copper-gold proposal.

Colombia lifts restrictions on 15 mining areas, but Quebradón still faces a permit hurdle

Why it matters: The regulatory change may improve the investment climate, but Quebradón's proposed US$2.5 billion development remains dependent on project-specific approvals.

By the numbers:
  • 15 areas — restrictions removed under Colombia's Resolution No. 40579

  • US$1.508 billion to US$178 million — mining foreign direct investment in 2022 and 2025, respectively

  • About 80,000 tonnes a year — copper production projection presented by AngloGold Ashanti on November 17, 2026

  • US$2.5 billion — estimated investment for Quebradón

Colombia has removed restrictions covering 15 areas designated for mining and agricultural protection, but the change has not cleared the permitting path for AngloGold Ashanti's Quebradón copper-gold project in Jericó, Antioquia. Resolution No. 40579, issued in late October 2026, does not confirm an environmental licence or other approvals for the proposed development.

The project remains subject to environmental, technical and administrative permits that have not been granted. Its projected construction and operating dates therefore remain contingent, rather than confirmed milestones.

Resolution follows a steep decline in mining investment

The government has linked the removal of restrictions to an effort to restore investor confidence. Mining foreign direct investment fell from US$1.508 billion in 2022 to US$178 million in 2025, according to the figures cited for the sector.

The resolution's broader regulatory change should not be read as a project-level approval. Quebradón's status depends on its own authorization process, and the available information does not establish that Resolution No. 40579 reverses earlier decisions affecting the project.

AngloGold Ashanti has estimated Quebradón would require US$2.5 billion in investment. Published production projections have varied: some estimates put annual copper output at 60,000 to 70,000 tonnes, while figures shared by the company on November 17, 2026, put it at about 80,000 tonnes. Reports also project annual exports of about US$1.5 billion. The differing production estimates mean the figures should be treated as projections, not a settled operating forecast.

Earlier regulatory decisions still frame the permit process

The National Environmental Licensing Authority (ANLA) archived Quebradón's environmental permit application in October 2021. In June 2025, Resolution 855 established a temporary natural-resource reserve in the area around the project, imposing restrictions on mining activity.

The information available does not confirm that the October 2026 measure reversed either decision or that Quebradón has received an environmental licence. AngloGold Ashanti has projected construction could begin in 2028, with operations starting in 2030–2031, but both dates depend on the required approvals. The company’s shares on the New York Stock Exchange were down 8.9% year to date as of November 19, 2026; that market performance does not alter the project's outstanding permitting requirements.