Marimaca wins Sprott committee approval for US$450m, but funds remain conditional

Marimaca’s Antofagasta oxide project is advancing through detailed engineering, while legal and closing steps still stand between approval and construction funding.

Marimaca wins Sprott committee approval for US$450m, but funds remain conditional

cruxinvestor.com

Why it matters: The proposed financing could fund construction of Marimaca’s oxide project, but committee approval does not make capital available or green-light the build.

By the numbers:
  • Up to US$450 million — proposed total package from Sprott

  • Up to US$425 million — project-finance facility

  • Up to US$25 million — proposed Sprott equity investment

  • US$100 million — initial draw available only after FID and satisfaction of requirements

Marimaca Copper has received approval from the investment committee of Sprott Resource Lending for a proposed financing package of up to US$450 million to build its Marimaca Oxide Deposit (MOD) project in Chile’s Antofagasta Region. The approval allows the parties to move toward definitive agreements; it does not complete the financing or authorize construction.

The package combines a project-finance facility of up to US$425 million with an equity investment of up to US$25 million from Sprott. Legal and financial reviews, execution of the agreements and other transaction conditions must be completed before closing. Marimaca said it will continue work on the definitive documentation and the structure of the construction financing.

First draw depends on investment decision

The first US$100 million draw would be available after Marimaca makes a Final Investment Decision (FID) and meets the specified requirements. Further disbursements would also remain subject to agreed conditions, so the committee’s approval does not provide immediate access to construction funds.

Proceeds may be used for MOD construction and commissioning costs, working capital, financing-related expenses and other general corporate purposes. The facility would have a 7.5-year term and a variable interest rate of 5.75% a year plus the greater of SOFR or 2.75%. Marimaca may capitalize up to 85% of interest costs during the availability period.

The proposed terms do not require copper-price hedging and include no cash-sweep mechanism or production-linked payments. The package also does not include an equity issue by Marimaca as part of the financing. Principal repayments would begin on March 31, 2031, through quarterly payments equal to 4% of the outstanding balance, including capitalized interest and other costs; the remaining balance would be due at maturity.

Pampa Medina exploration adds to the development context

Marimaca said it is progressing detailed engineering, field activities and construction preparation for the MOD, with those activities expected to increase over the coming months. The company had selected a preferred lender in October 2026 to negotiate a US$375 million to US$400 million loan, before reaching the current proposal with Sprott.

Marimaca also linked Sprott’s support to its wider growth strategy, including exploration at Pampa Medina and Madrugador in the Sierra de Medina area, about 30 kilometres from the MOD. The company reported that recent drilling there identified extensions of oxide mineralization and high-grade sulphide mineralization at depth. Those exploration results are separate from the financing approval and do not alter the conditions attached to the proposed facility.

Marimaca chair Nico Cookson described the approval as a step in moving the MOD toward development. Sprott partner Corey Posesorski said the project had a defined development path and an experienced team. The next steps for the financing are completion of definitive documentation and closing conditions; the FID remains necessary before the initial draw can be accessed.