Codelco reports US$377m loss as US$4.82bn asset write-down weighs on results

Higher copper prices lifted EBITDA, but a 9% fall in own production leaves the state miner’s operating recovery unfinished.

Codelco reports US$377m loss as US$4.82bn asset write-down weighs on results

Why it matters: Codelco’s earnings and fiscal contributions strengthened, but lower mine output and a large asset write-down underline the pressure on its operating base and investment capacity.

By the numbers:
  • US$377 million — net loss for January-September 2026.

  • US$4.82 billion — asset impairment recorded at three divisions.

  • US$7.496 billion — EBITDA, up 80% year on year.

  • 853,000 tonnes — own copper production, down 9% year on year.

Codelco recorded a US$377 million net loss in the first nine months of 2026, chiefly after recognising US$4.82 billion in asset impairments at its Chuquicamata, Salvador and Gabriela Mistral divisions. The result contrasted with an 80% increase in EBITDA to US$7.496 billion, while own copper production fell 9% to 853,000 tonnes.

The Chilean state miner also reported an extraordinary US$123 million inventory adjustment. Despite the net loss, its contributions to the state rose 57% to US$1.945 billion, exceeding the US$1.778 billion paid during all of 2025.

Impairments offset stronger operating earnings

The asset write-down reflects a reduction in the estimated recoverable value of assets, rather than necessarily an immediate cash outflow. Mining impairment assessments can account for factors including available reserves, ore grades, operating costs, future investment, mine life and long-term price assumptions.

The company’s impairment recognition covered three divisions: Chuquicamata, Salvador and Gabriela Mistral. The company said the effect on each operation depends on the technical and financial information used in the assessment. The charge comes as Codelco faces substantial capital requirements to modernise its divisions and sustain production.

Higher international copper prices supported operating performance and helped lift EBITDA, but the gain did not prevent a net loss once the impairments and inventory adjustment were recognised. Codelco’s results also show why operating earnings, net income and state payments can move differently: fiscal contributions rose even as the company reported a loss.

Own production remained below 2025 levels

Codelco’s own operations produced 853,000 tonnes of fine copper from January to September, compared with 937,000 tonnes in the same period of 2025. Including its interests in other mining companies, attributable production totalled 933,000 tonnes, down from 1.016 million tonnes a year earlier. Those interests include 49% of Minera El Abra, 20% of Anglo American Sur and 10% of Quebrada Blanca.

The company’s production decline moderated from 11% in the first half to 9% through September, but output remained below the prior-year level. During the first half, constraints at El Teniente, Chuquicamata and Ministro Hales included operating restrictions, maintenance and lower ore grades.

Capital needs accompany recovery priorities

In August 2026, the government authorised the capitalisation of all Codelco profits from 2025, retaining approximately US$2.422 billion within the company to support its balance sheet, financial commitments and investment needs. That capitalisation followed a year in which state contributions totalled US$1.778 billion.

Codelco’s stated operational priorities include recovering performance at El Teniente, developing Chuquicamata Underground, consolidating Rajo Inca and continuing investment needed to secure future mineral supply. These programmes must be balanced against existing financial commitments and the need to generate revenue. The September results do not specify how the impairments will affect each division’s future investment plans; the company’s production recovery and the assumptions behind its asset valuations remain key factors to monitor.